NOTE : IT IS RECOMMENDED THAT ONE SHOULD READ THESE POINTS IN DETAIL FROM THE BOOKS (which ever interests you more) AND ONLY AFTER YOU HAVE FINISHED A THOROUGH READING, YOU CAN GO THROUGH THESE POINTS FOR CONSOLIDATION.
- Reestimate : atleast once.
- Schedule Network Analysis is a technique that generates the Project Schedule Model.
- Standard Deviation tells you how uncertain the schedule is.
- You want to see scheduling flexibility - Critical Path .
- If the number of resources are most important and not the cost and schedule - Perform Resource Optimization.
- Crashing also has some risk in it.
- Ask team members about their estimate of time for their activities and enter that in calendar - Develop Schedule
- You are drawing a network diagram - PDM
- If you have to shorten an activity - pick the one on critical path - if there are more then one - pick the one who is coming first - not the one with bigger duration.
- As part of the estimate activity duration process, reserves are created (to cover risk)
- Schedule is not finalized until after Schedule Compression
- Compress Schedule - finalize - gain approval
- Rolling Wave Planning : should be used where it is not possible to plan in any other way.
- Activities are broken down to a level where they can be estimated accurately.
- Activity List : lower then the WBS
- Activity Attribute : description of each activity (any predecessor activity, successor activity, constraints, resources for that activity etc.)
- Network Diagram : visualize the way activities relate
- PDM : activities in rectangle, relationship as arrow, AON
- Activity Attribute should list the predecessor and successor
- Resources are people, equipment, location. anything that you need to do an activity.
- Every activity in the activity list needs to have resources assigned to it.
- Resource Calendar : what resources can you use for your project. when are they available to you.
- Parametric Estimation : put the data about your project in a spread sheet , formula, database or computer program.
- Analogous Estimation : trends, historical data, previous project.
- Develop Schedule : all the outputs from the other time management processes are input to this process
- Sequence Activity : see the dependencies between activities - create a diagram of the activity network
- Critical Path - string of activities - if anyone of them is delayed - the project will get delayed
- FLOAT = SLACK = how much extra time can you take for doing that activity without delaying the project
- Float = how much extra time do you have
- Low float can be a problem
- ES/ EF (early start / early finish) : freedom you have to move the start date of that activity without causing any problem to the project
- LS/ LF (late start / late finish) : activity with large late start or late finish date means you have more options
- Fast Tracking : work in parallel, risk, may have to redo
- Crashing : add resources, more cost, expensive
- Update the resource requirement OR update the activity attribute : no CCB
- Project Calendar : working days for the team member, holidays, non working days, planned training, dates that could affect the project etc.
- Any time you generate data for your project - add it to your OPA
- How long an activity can slip before the whole project is delayed : FLOAT.
- Plugging data into a database or spreadsheet : Parametric
- Kind of analysis where you ask many questions : what-if analysis.
- Duration : calendar time, how long the activity takes
- Efforts : person hours. it takes two people 6 hours to complete a work. duration = 6 hours. efforts = 2 * 6 = 12 hours
- Resource estimate : how many people + other resources for one activity
No comments:
Post a Comment